Wizdom Networks Website - Development Plan & Estimated Timelines
Version: 1.0
Date: February 3, 2025
1️⃣ Project Overview
The Wizdom Networks website is undergoing structured development to ensure:
✅ MVC Architecture Compliance – Modular and scalable design.
✅ Efficient UI/UX Implementation – Fully responsive, accessible, and easy to navigate.
✅ Structured Versioning & Tracking – Clear change management and updates.
✅ Security & Performance Optimization – Secure database interactions, error handling, and logging.
2️⃣ Development Phases & Timelines
Below is the detailed development roadmap aligned with best practices:
🔹 Phase 1: Core Architecture & Setup (1-2 Weeks)
✅ Set Up File Structure & Core MVC Components (Completed)
✅ Implement Base Controllers & Routing System (Completed)
✅ Configure head.php, main.php, and footer.php for dynamic loading (Completed)
✅ Implement View::render() for all partials & templates (Completed)
✅ Ensure global styles are correctly applied (Completed)
⏳ Estimated Completion: Already Completed
🔹 Phase 2: UI/UX & Frontend Enhancements (2-4 Weeks)
📌 Tasks:
1️⃣ Refactor Slider System for Modular Use (Completed)
2️⃣ Ensure Global & Page-Specific Stylesheets Are Dynamically Loaded (Completed)
3️⃣ Enhance Accessibility (ARIA, Keyboard Navigation, Semantic HTML) (🔄 In Progress)
4️⃣ Finalize Slider Enhancements:
- Implement Grayscale Effect (Completed)
- Fix Indicator Colors Dynamically (Completed)
- Add ARIA & Accessibility Enhancements (🔄 In Progress)
- Make
object-fitconfigurable for images (Completed) - Ensure error logging for missing configurations (Completed)
5️⃣ Optimize Bootstrap Components for Mobile & Desktop Consistency (🔄 In Progress)
⏳ Estimated Completion: 2 Weeks Remaining
🔹 Phase 3: Page Development & Integration (3-5 Weeks)
📌 Tasks:
1️⃣ Homepage Finalization
- Implement optimized hero section & sliders (🔄 In Progress)
- Load page-specific styles dynamically (Completed)
2️⃣ Services Pages
- Implement modular content structure for IT services.
- Ensure database-driven content for easier updates (Future Enhancement).
3️⃣ Contact Page
- Implement secure contact form with PHPMailer.
- Validate inputs & ensure security against spam attacks.
- Ensure error handling & logging for contact form submissions.
4️⃣ Navigation System Enhancements
- Implement breadcrumb navigation for enhanced UX.
- Ensure dropdowns & mobile navigation function properly.
⏳ Estimated Completion: 3-5 Weeks
🔹 Phase 4: Security, Performance & Testing (2-3 Weeks)
📌 Tasks:
1️⃣ Security Enhancements
- Sanitize & validate all user input.
- Implement CSRF protection on all forms.
- Ensure prepared statements in all database queries.
2️⃣ Performance Optimization
- Minimize & optimize stylesheets and scripts.
- Implement lazy loading for images & assets.
- Enable Gzip compression & caching rules.
3️⃣ Testing & Debugging
- Functional Testing ✅
- Unit Testing for Controllers ✅
- UI Testing Across Devices ✅
- Accessibility Testing ✅
- Final Bug Fixes & Adjustments ✅
⏳ Estimated Completion: 2-3 Weeks
3️⃣ Final Deployment & Launch (1 Week)
📌 Tasks:
✅ Deploy to Production Server
✅ Ensure SSL & Security Headers Are Applied
✅ Final Performance & Speed Tests
✅ Pre-Launch Checklist Review
✅ Client Review & Sign-Off
⏳ Estimated Completion: 1 Week
4️⃣ Estimated Total Timeline
| Phase | Estimated Duration |
|---|---|
| Phase 1: Core Setup | ✅ Completed |
| Phase 2: UI/UX Enhancements | 2 Weeks Remaining |
| Phase 3: Page Development | 3-5 Weeks |
| Phase 4: Security & Testing | 2-3 Weeks |
| Phase 5: Deployment & Launch | 1 Week |
🎯 Total Estimated Time Remaining: 6-9 Weeks
5️⃣ Next Steps
🔹 Immediate Focus:
✅ Finalize remaining Slider Enhancements
✅ Implement Home Page UI Fixes
✅ Ensure Accessibility Best Practices Are Met
🔹 Upcoming Tasks:
✅ Start Final Page Integration (Contact, Services)
✅ Begin Security & Performance Testing
Final Thoughts
This development plan ensures structured progress, avoids bottlenecks, and aligns with best practices. Let me know if you’d like any refinements! 🚀