Wizdom Networks Website - Development Plan & Estimated Timelines

Version: 1.0
Date: February 3, 2025


1 Project Overview

The Wizdom Networks website is undergoing structured development to ensure:
MVC Architecture Compliance Modular and scalable design.
Efficient UI/UX Implementation Fully responsive, accessible, and easy to navigate.
Structured Versioning & Tracking Clear change management and updates.
Security & Performance Optimization Secure database interactions, error handling, and logging.


2 Development Phases & Timelines

Below is the detailed development roadmap aligned with best practices:

🔹 Phase 1: Core Architecture & Setup (1-2 Weeks)

Set Up File Structure & Core MVC Components (Completed)
Implement Base Controllers & Routing System (Completed)
Configure head.php, main.php, and footer.php for dynamic loading (Completed)
Implement View::render() for all partials & templates (Completed)
Ensure global styles are correctly applied (Completed)

Estimated Completion: Already Completed


🔹 Phase 2: UI/UX & Frontend Enhancements (2-4 Weeks)

📌 Tasks:
1 Refactor Slider System for Modular Use (Completed)
2 Ensure Global & Page-Specific Stylesheets Are Dynamically Loaded (Completed)
3 Enhance Accessibility (ARIA, Keyboard Navigation, Semantic HTML) (🔄 In Progress)
4 Finalize Slider Enhancements:

  • Implement Grayscale Effect (Completed)
  • Fix Indicator Colors Dynamically (Completed)
  • Add ARIA & Accessibility Enhancements (🔄 In Progress)
  • Make object-fit configurable for images (Completed)
  • Ensure error logging for missing configurations (Completed)
    5 Optimize Bootstrap Components for Mobile & Desktop Consistency (🔄 In Progress)

Estimated Completion: 2 Weeks Remaining


🔹 Phase 3: Page Development & Integration (3-5 Weeks)

📌 Tasks:
1 Homepage Finalization

  • Implement optimized hero section & sliders (🔄 In Progress)
  • Load page-specific styles dynamically (Completed)

2 Services Pages

  • Implement modular content structure for IT services.
  • Ensure database-driven content for easier updates (Future Enhancement).

3 Contact Page

  • Implement secure contact form with PHPMailer.
  • Validate inputs & ensure security against spam attacks.
  • Ensure error handling & logging for contact form submissions.

4 Navigation System Enhancements

  • Implement breadcrumb navigation for enhanced UX.
  • Ensure dropdowns & mobile navigation function properly.

Estimated Completion: 3-5 Weeks


🔹 Phase 4: Security, Performance & Testing (2-3 Weeks)

📌 Tasks:
1 Security Enhancements

  • Sanitize & validate all user input.
  • Implement CSRF protection on all forms.
  • Ensure prepared statements in all database queries.

2 Performance Optimization

  • Minimize & optimize stylesheets and scripts.
  • Implement lazy loading for images & assets.
  • Enable Gzip compression & caching rules.

3 Testing & Debugging

  • Functional Testing
  • Unit Testing for Controllers
  • UI Testing Across Devices
  • Accessibility Testing
  • Final Bug Fixes & Adjustments

Estimated Completion: 2-3 Weeks


3 Final Deployment & Launch (1 Week)

📌 Tasks:
Deploy to Production Server
Ensure SSL & Security Headers Are Applied
Final Performance & Speed Tests
Pre-Launch Checklist Review
Client Review & Sign-Off

Estimated Completion: 1 Week


4 Estimated Total Timeline

Phase Estimated Duration
Phase 1: Core Setup Completed
Phase 2: UI/UX Enhancements 2 Weeks Remaining
Phase 3: Page Development 3-5 Weeks
Phase 4: Security & Testing 2-3 Weeks
Phase 5: Deployment & Launch 1 Week

🎯 Total Estimated Time Remaining: 6-9 Weeks


5 Next Steps

🔹 Immediate Focus:
Finalize remaining Slider Enhancements
Implement Home Page UI Fixes
Ensure Accessibility Best Practices Are Met

🔹 Upcoming Tasks:
Start Final Page Integration (Contact, Services)
Begin Security & Performance Testing


Final Thoughts

This development plan ensures structured progress, avoids bottlenecks, and aligns with best practices. Let me know if youd like any refinements! 🚀